Latest progress - Cross River State - June 2019

Body

43 Completed WC1 Projects; 9 Ongoing WC1 Projects; 8 Completed WC2 Projects and 3 Ongoing WC2 Projects in Cross River State

Forty-Three (43) Micro Projects (Water Schemes, School Blocks, Agro Mills, Civic Centres, Open Markets Stalls) under Works Contract 1 (WC1) have been successfully Completed and handed over to beneficiaries in Obudu, Abi and Biase Local Government Areas of Cross River State. Nine (9) other micro projects under WC1 are under construction presently. Eight (8) micro projects are yet to be started under WC1.

Eight (8) micro projects (Water Schemes, Open Market) under WC2 have been Completed and awaiting Provisional Acceptance (handing over to beneficiaries). The Projects are spread across Obudu, Abi and Biase Local Government Areas of Cross River State. Three (3) micro projects under WC2 are under Construction present in Abi and Obudu Local Governments of the State.

Thirty (30) Projects under WC2 are yet to be awarded.

ANTICIPATED BENEFITS OF MICRO PROJECTS TO THE COMMUNITIES – CROSS RIVER STATE

S/No

WC [1/2]

LGA

Community

Project Type

Project Status

Project Benefits

1

WC1

Biase

Akpet 1

School Block

Substructure Blockwork

i.                                Academic Infrastructure: The project is an addition to the academic infrastructure in the community in particular and in the state at large. Has a capacity of 60 students

ii.                              Psychological Boost: The students are boosted psychologically to work harder due to the decent learning environment.

iii.                            Overall Improvement in education standards in the LGA envisaged.

2

WC1

Biase

Adim

School Block

Substructure Blockwork

i.                                Academic Infrastructure – The project is an addition to the academic infrastructure in the community in particular and in the state at large. Has a capacity of 60 students.

ii.                              Psychological Boost – The students are boosted psychologically to work harder due to the decent learning environment.

iii.                            Overall Improvement in education standards in the LGA envisaged.

 

3

WC1

Biase

Amarurang

Health Centre

Blockwork at lintel level.

i.                                Additional Health infrastructure to the village and the state at large. Has capacity for 6 beds. Primary health care facility is brought closer to people.

ii.                              Reduced mortality rate is anticipated among the villagers with the closeness to health care facility.

iii.                            Socio-economically, the facility will create a number of jobs for skilled and unskilled persons in the village. Having a health facility close by, the people will access medical care readily and maintain good health thus resulting higher man days of work per capita.

 

4

WC1

Biase

Utuma

Open Market

Roofing in progress

i.                                Boost in Commercial Activities – The community does not have any built-up shops but only trade in the open. The completion of this project will provide the first built shops in the community. This will boost commercial activities in the community and improve livelihood.

ii.                              Socioeconomically, the market infrastructure will improve the financial standing of the community through rents derived from leasing the facility/ building.

 

5

WC1

Biase

Etana

School Block

Substructure Blockwork

i.                                Academic Infrastructure – The project is an addition to the academic infrastructure in the community in particular and in the state at large. Has a capacity of 60 students Psychological Boost – The students are boosted psychologically to work harder due to the decent learning environment.

ii.                              Overall Improvement in education standards in the LGA and State at large.

iii.                            Psychological Boost to the children in the Community resulting in higher school enrolment.

 

6

WC1

Biase

Umuolor

School Block

Substructure Blockwork

i.              Academic Infrastructure – The project is an addition to the academic infrastructure in the community in particular and in the state at large. Has a capacity of 60 students

ii.            Psychological Boost – The students are boosted psychologically to work harder due to the decent learning environment.

iii.          Overall Improvement in education standards in the LGA and State at large.

 

7

WC1

Biase

Iwuru

Lock-up Stalls

Blockwork at lintel level

i.              Additional Commercial Infrastructure in the community – The community market is big. Most of the traders trade in the open. After the completion of this project, it is expected that the traders will operate in a more conducive environment, and it is important to be mentioned that those who get the lock up shops will not have to move their wares as frequently as they do now.

ii.            Socioeconomically, the lock up stalls, when leased out will improve the socioeconomic status of the community through rents derived from leasing the facility.

 

8

WC1

Biase

Akpet Central

Water Scheme

Project Completed

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent by people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of people.

 

9

WC1

Biase

Ugbem

Water Scheme

Borehole Drilled/Civil Infrastructure started

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent in search of water. This saved time can be invested in doing some other economic activities that will be a positive addition to people’s socioeconomic status

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

 

10

WC1

Biase

Etono Central

Open Market

Provisionally handed over

i.              Boost in Commercial Activities – The community does not have any built shops but only trade in the open. The completion of this project will provide the first built shops in the community. This will boost commercial activities in the community and improve livelihood.

ii.            Socioeconomically, the market infrastructure will improve the financial standing of the community through rents derived from leasing the facility.

 

11

WC2

Abi

 Igonigoni

Water Scheme

Project Completed. Awaiting Provisional Acceptance.

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent by people in search of water. This saved time can be invested in doing some other economic activities that will be a positive addition to the socioeconomic status of the people.

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

 

12

WC2

Abi

Bazaure

Water Scheme

Project Completed. Awaiting Provisional Acceptance

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent by people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

 

13

WC2

Abi

Usumutong

Water Scheme

Project Completed. Awaiting Provisional Acceptance

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent by the people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

14

WC2

Biase

Abaribare

Water Scheme

Project Completed. Awaiting Provisional Acceptance

i.              Improved Water Supply Infrastructure in the Community and State at large.

ii.            Socioeconomically, the water scheme will reduce the time spent by the people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.          Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people

 

15

WC2

Obudu

Ubong Ubong

Water Scheme

Completed. Awaiting Provisional Acceptance

i.                                Improved Water Supply Infrastructure in the Community and State at large.

ii.                              Socioeconomically, the water scheme will reduce the time spent by the people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.                            Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

 

16

WC2

Obudu

Bebuagbong

Water Scheme

Completed. Awaiting Provisional Acceptance.

i.                                Improved Water Supply Infrastructure in the Community and State at large.

ii.                              Socioeconomically, the water scheme will reduce the time spent by the people in search of water. This saved time can be invested in doing some other economic activities that will add positively to the socioeconomic status of the people.

iii.                            Improved Health Conditions – Water is life, so the saying goes. Where there is adequate water supply, sanitation will be good, resulting in good health of the people.

 

17

WC2

Abi

Igbo Imabana

Open Market Stalls

Roofing Stage

i.                                Boost in Commercial Activities – The community does not have any built shops but only trade in the open. The completion of this project will provide the first built shops in the community. This will boost commercial activities in the community and improve livelihood.

ii.                              Socioeconomically, the market infrastructure will improve the financial standing of the community through rents derived from leasing the facility.